How To Create S Curve In Microsoft Project 2016

Ms Project is a powerful project management tool to plan, monitor, control, analyse and forecast project's status, progress and performance.

Ms Project has Earned Value Analysis that allows us to plot S-Curve chart displaying cumulative cost, labour hours or other quantities plotted against project's time span. But I came across a question asked by my student, i.e. how to display S-Curve chart with percentage complete against the time, side by side comparing the progress between your baseline and actual completion.

In this tutorial we will show walk you through how to create a chart to display the percentage completion of Baseline Cumulative Work and Cumulative Actual Work against the time.

Here is the step:

1. In Ms Project, select Report > Visual Reports > Baseline Work Report.

2. Click Edit Template button.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

3. At the Field Picker dialog box, select field Baseline Cumulative Work, click Add

4. At the Field Picker dialog box, select field Cumulative Actual Work, click Add.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

5. Then click Edit Template.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

6. The Visual Report is generated and opened in Excel Program. Select Assignment Usage worksheet.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

7. In Excel Program, change the PivotTable fields to as image below.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

8. Expand the Year, Quarter and Week fields. You may filter and modify the data as you want.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

9. For our case, we will:

  • Hide the Quarter column: right click anywhere at Year/Quarter/Week column, choose Show/Hide Fields > untick Quarter
  • Hide the value for Year 2019

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

10. Your PivotTable will display as shown below.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

Now, we want to duplicate the table and change the values to percentage. Then do the following:

11. Copy the table and Paste As Value to the empty column on the right.

  • Delete the date for each week.
  • Change the Cumulative Actual Works Grand total to 5220

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

12. Select cell in the first row of each column and enter the following formula.

For Cell I5:=C5/$I$23
For Cell J5:=D5/$J$23
For Cell K5:=E5/$K$23

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

13. Copy down the formula, and format the value to percentage style.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

14. Highlight the data and create a Line chart.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

15. Let's modify the axis to change the maximum value to 100%.

Right click at the vertical axis, choose Format Axis.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

16. In Axis Options, change maximum value to 1.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

17. The chart has now showing Percentage work completed for Baseline, Actual, Planning against the time.

Display Baseline and Actual Percent Completed with S-Curve Chart in Microsoft Project tutorial Melaka Puchong Selangor Malaysia

 Here are the sample files to download: Ms Project Sample, Excel Report Sample

By Chee SK   | LinkedIn

Cempaka Technology Sdn Bhd

Pusat Latihan Komputer Cempaka
~Your HRDC Premiere Training Provider~
Unit 6, Level 4, SetiaWalk Mall (Block K), SetiaWalk, Persiaran Wawasan, Pusat Bandar Puchong, 47160 Puchong, Selangor, Malaysia.
Tel: 603-80684461, Fax: 603-80684240
1-28, Jalan PM4, Plaza Mahkota, 75000 Melaka, Malaysia
Tel: 606-2835955, Fax: 606-2845955

How To Create S Curve In Microsoft Project 2016

Source: https://www.cemtech.biz/project-tutorial-baseline-actual-completed-s-curve-chart

Posted by: singhhows2000.blogspot.com

0 Response to "How To Create S Curve In Microsoft Project 2016"

Post a Comment

Iklan Atas Artikel

Iklan Tengah Artikel 1

Iklan Tengah Artikel 2

Iklan Bawah Artikel